Updates from Green Line Design Working Group meeting

  • Post category:Green Line

The Green Line Extension Design Working Group met on Nov 15 and got an overview of station designs, including new renderings of the future Lechmere station. (Our Green Line map is updated with the latest images and plans.)
We also met members from the new Advanced Preliminary Engineering and Final Design team, primarily AECOM and HNTB. Phase 1 construction begins this month. For the next phases, here are the upcoming milestones for Construction Manager/General Contractor selection:

  • Issue LOI/RFQ: Fall 2012/ Winter 2013
  • Issue RFP: Winter 2013
  • RFP Due: Winter 2013
  • CM/GC Presentations: Winter 2013
  • CM/GC Award: Spring 2013
  • CM/GC NTP for Prof. Srvcs.: Spring 2013

Download the slides from the meeting (PDF).